Wing 62
Time logged: 258.3 hrs
- Entry Time spent
- Hangar Washing & Aileron Rigging 2 hrs
- Post Wing Mounting Work - Part 5 - Installing Ailerons 2 hrs
- Post Wing Mounting Work - Part 4 - The Boost Pump Saga 14 hrs
- Post Wing Mounting Work - Part 3 4 hrs
- Post Wing Mounting Work - Part 2 0.5 hrs
- Mounting the Left Wing - Part 2 2.5 hrs
- Mounting the Left Wing - Part 1 5 hrs
- Mounting the Right Wing - Part 4 4.3 hrs
- Mounting the Right Wing - Part 3 4.3 hrs
- Mounting the Right Wing - Part 2 2 hrs
- Mounting the Right Wing 4 hrs
- Wing Mounting Prep - Rod Ends 4 hrs
- Wing Mounting Jigs 9 hrs
- Re-installing GTP 59 (OAT Probe) 0.5 hrs
- Installing GTP 59 (OAT Probe) 0.3 hrs
- Re-installing boost pumps 2 hrs
- Remove Boost Pumps 1 hrs
- Takes a village... flaring fuel lines 3 hrs
- Fuel boost pump plumbing test 2.5 hrs
- Boost Pump Upgrade 13 hrs
- Left tank: part 3 (leak test and install) 3.5 hrs
- Left wing: aileron and flap fully riveted 1 hrs
- Left wing: nav light is on 1 hrs
- Left wing: wing tip 3 hrs
- Left tank: part 2 (Sealing back channel) 4 hrs
- Remaking left landing light cover - Part 2 5 hrs
- Left tank, part 1 (Sealing ribs and skin) 10 hrs
- Left tank match drilling, left wing root trailing edge 3 hrs
- Left wing skin misc clean up, and discussing panel with MPB 2.5 hrs
- Completing the right fuel tank 3 hrs
- Remaking left landing light cover - Part 1 6 hrs
- Left wing: landing light cover and fuel level sender 2 hrs
- Mocking left tank and filling rivets 4 hrs
- Right wing: lights and lens, wing tip and wing stand 12 hrs
- Prosealing the right fuel tank, left wing leading edge & lights 15 hrs
- Left top skin, and landing lights 2 hrs
- Misc work, but mostly fuel tank 2 hrs
- Right leading edge and fuel tank prep 8 hrs
- Right leading edge done 4 hrs
- Built the left flap 1.3 hrs
- Fuselage kit arrived, and left aileron 5 hrs
- Installing pitot tube 5 hrs
- Left bottom skin riveted 3 hrs
- Left bottom skin clecoed, and some rivet drilling 2 hrs
- Right aileron, flap, trailing edge, and left spar 3 hrs
- Right leading edge skin damage 1.5 hrs
- Lots of things going on the right wing, and starting on the left 9 hrs
- Right aileron part prep 2 hrs
- Right leading edge done 2 hrs
- Clecoing left ribs, and update on rivet gun 3 hrs
- Right top skin and leading edge 8 hrs
- Rib 9 fix, and starting right top skin 4 hrs
- right wing harness 4 hrs
- Working on right top skin and left ribs 2.3 hrs
- Right bottom skin riveted 3 hrs
- Right bottom skin fitting and an successful experiment 5.5 hrs
- Right spar assembly 4 complete, started assmebly 3 4 hrs
- Starting to rivet ribs to spar 3 hrs
- Cleaning left ribs, and found a crack 3.5 hrs
- Right wing ribs, and lots of debur 7 hrs
- Getting started on the right wing (rear spar and a few ribs) 6 hrs
- Wing kit and dimple template 0.2 hrs